College Station's school board gave its approval to the price of some key district projects.

Guaranteed maximum prices were signed off on for the new Creek View Elementary -- which will go near Cypress Grove -- along with renovations at athletics facilities.

In total, Creek View will cost $14.3 million before architect, testing and other fees.

The athletics upgrades, which include new field turf, drainage and a running track, will cost $6.6 million before those additonal fees.

For all of the approved projects, the total price tag is about $22 million, which is below what was originally planned.